SET invests in the renewal of its slipway at the Genthin site

Around 120 vessels per year are slipped here to carry out maintenance, repairs, and statutory inspections.

In June 2025, the engineering office Fanger from Magdeburg was once again commissioned with planning, project execution, tendering, and construction supervision, an important step for the successful implementation of this project.

However, wear and damage to the rails have recently led to outages and increasing maintenance costs. SET is now investing specifically in the future:

  • Start of construction: August 2026
  • Construction period: approx. 4 months
  • Renewal of all 8 rail pairs on land and underwater

This measure represents the largest investment at the site in over 40 years, a clear commitment to inland shipping and the future of shipyards.

Many thanks to the shareholder family for their trust, support, and genuine commitment.

In the picture from left to right: Christian Fanger (Fanger Engineering Office), Fabian Karbe (Managing Director SET GmbH), Thomas Foltys (Branch Manager Eurovia Verkehrsbau GmbH Magdeburg), Jan Albrecht (Technical Director Eurovia Verkehrsbau GmbH Magdeburg)
 

Pressekontakt

Wenden Sie sich gerne an uns!

Für weitere Fragen rund um die Themen Presse, Filmmaterial und Fotos wenden Sie sich bitte direkt an unseren Pressekontakt.

Kira Rönner
 +49 471 80960 995
  k.roenner@hr-gruppe.de