After the SPMTs on the pontoon had taken on the load of the bridge section to be removed, the last flame cut was made late at night and the historic swing bridge was thus prepared for removal.
On Saturday morning, the pontoon was drained as planned and the pontoon, including SPMTs and bridge section, was raised to the required height. The bridge section was then rotated on the pontoon using the SPMTs.
Through the Kaiserhafen the pontoon went to the ABC Peninsula. Once there, the swing bridge with the SPMTs was driven onto the heavy-duty platform on land.